Energy

Case Study: Hurricane Harvey

AEP_Hurricane-Harvey-1

In August 2017, Hurricane Harvey damaged several transmission line structures from Aransas Pass to Port Aransas. TTL was engaged by American Electric Power (AEP) to perform a geotechnical investigation and provide engineering recommendations by mid-November 2017. Using an unmanned Arial vehicle, our professional staff immediately assessed the site to identify challenges and to formulate a strategy that would result in on-time delivery of our design recommendations.

The geotechnical investigation program consisted of performing 32 soil borings and 26 Cone Penetrometer Test (CPT). Locations of the soil borings and CPT tests were selected by the design team.  The boring and CPT test locations were near Mangrove plant, an endangered plant, in water and in wetlands. Borings located in the water were drilled from a barge. Airboats were used to maneuver the barge from one location to the other due to shallow water depth.  A Marsh-buggy, an amphibious vehicle, was used to access the borings located near mangroves to avoid plant damage. The remaining soil borings and CPT tests were completed using TTL’s all-terrain equipment.

TTL’s professional field staff performed borings and CPT tests in accordance with industry standards, and the laboratory testing program was completed in our accredited laboratories. The engineering report was submitted on schedule and included axial and lateral design parameters for deep foundations and applicable construction considerations.

Other Sample Projects:

AEP Service Center, Corpus Christi, TX

AEP Service Center, Corpus Christi, TX

AEP is constructing a new state-of-the-art service center in Corpus Christi, Texas that will replace two AEP facilities in the area. TTL was engaged by American Electric Power (AEP) to perform a geotechnical investigation and provide engineering recommendations by mid-November of 2017. The facility will be approximately 94,000 square feet and will house 150 employees from…

Linde Gas

Linde Gas

TTL performed construction materials testing services for this $41 million project for Linde Gas in Adel, Georgia. The project was the largest capital investment in Cook County to date and joined 10 other sites in Georgia with an estimated 570 employees statewide. Linde Group is headquartered in Munich, Germany and produces and sells atmospheric gases…

South Nashville Natural Gas Pipeline

South Nashville Natural Gas Pipeline

Construction for this project included a 12 mile, 20-inch diameter pipeline, a 1.5 mile, 12-inch lateral pipeline, three pressure regulation stations, and one pipeline interconnection station for our client, Energy Land & Infrastructure, LLC. Project services included drilling borings in areas with materials susceptible to landslides along planned HDD alignments and providing mitigation recommendations.

BP Facility, Decatur, AL

BP Facility, Decatur, AL

TTL performed a geotechnical investigation, construction materials testing, and special inspections on the 100,000-square-foot facility in Decatur, AL. Services included soils and concrete sample collection, testing, and analysis. TTL also performed steel inspection.